It was all just too much action for some.
Thursday, 29 March 2018
Floor, roof and footpath
The first underfloor insulation was laid, the roof was nearly completed and even the footpath outside started to be replaced.
It was all just too much action for some.
It was all just too much action for some.
Wednesday, 28 March 2018
One wall down and one wall up
Malcolm Jenkins from Recycled Rimu Furniture in Carterton is taking down (and taking away) the old back wall while Ryan is erecting the wall between the ensuite and new kitchen area.
Tuesday, 27 March 2018
Wednesday, 21 March 2018
Friday, 16 March 2018
Thursday, 15 March 2018
Glass in doors
Glass was put in the doors today. Dean was working alone so only he and Minnie attended the safety briefing. He put the rafters up.
Wednesday, 14 March 2018
Tuesday, 13 March 2018
First skylights installed
There will be 7 skylights in all, all in the covered parts of the extension verandah. We night add one in the front verandah too.
Friday, 9 March 2018
It's all coming together
Dean, Ryan and Cody worked on a variety of inside and outside tasks today. Next week, while we are away in Northland, the last two windows and the bifold doors for the extension should be installed.
Thursday, 8 March 2018
Inside work
Poor weather over the last couple of days so lots done indoors: Pantry framework, ensuite and kitchen floor constructed in the old laundry area and the opening made for the first of the two internal french doors.
Tuesday, 6 March 2018
Window day!!
As well as the first four new windows being installed in the extension today, Peter Allum installed the round leadlight window in the front door.
And Ryan and Cody installed the first four new windows in the extension.
And Ryan and Cody installed the first four new windows in the extension.
Subscribe to:
Posts (Atom)