Friday 27 April 2018

Cabling started

Shaun started some of the data, coax and HDMI cabling.

Ryan finished the ceiling preparation

And the ensuite is now ready for the shower tray and then gib

Thursday 26 April 2018

Breakthrough

Dean opened up the doorway from the bedroom to the ensuite.



Thursday 19 April 2018

Friday 13 April 2018

Floor almost finished

Just need a couple more boards to finish the job.

And this afternoon one more structural beam was added so that we can avoid having to have a support wall in the middle of the room. The woodburner flue was going to go up next to that wall so now we can move the woodburner to a sidewall and the old kitchen range can take pride of place at the end of the kitchen island.


Thursday 12 April 2018

Even the kitchen sink..

The kitchen unit has been removed and temporarily installed in a floored part of the room.


And Ryan was back and continuing the floorboards.

Wednesday 11 April 2018

Plumbing and flooring

Kitchen
Ensuite
Ensuite

The Ropers continued the plumbing work and Dean continued the flooring.

Tuesday 10 April 2018

Plumbing started

Dean continued laying floorboards and Wayne Roper arrived to begin the plumbing.



Friday 6 April 2018

Thursday 5 April 2018

Floorboards, floorboards, floorboards...

Ryan spent the day laying down floorboards.

 And Dean started preparing the area for the woodburner.