Thursday, 31 May 2018

Plastering started

After a couple of days when there was just Dean here, today we had 3 plasterers, 2 builders, 1 joinery delivery man, 1 glazier and a plumber!

The plasterers started, the last set of french doors and the two sets of internal french doors were delivered, the external french doors were installed and the doorway from the hall to the dining room was opened up for the french doors.


Tuesday, 29 May 2018

Some of the decking timber arrived

Dean started gibbing the ensuite today.

The  timber for the decking structure was delivered.

Friday, 25 May 2018

Room gibbing finished

Just the ensuite to go, then the dining room and the last part of the hall.

Thursday, 24 May 2018

Friday, 18 May 2018

Tuesday, 15 May 2018

Weatherboards around verandah

While they wait for the batts to arrive Dean and Ryan are finishing off external work.

Friday, 11 May 2018

Finishing the weatherboards

Dean and Ryan working outside today to begin the completion of the weatherboards.