After a couple of days when there was just Dean here, today we had 3 plasterers, 2 builders, 1 joinery delivery man, 1 glazier and a plumber!
The plasterers started, the last set of french doors and the two sets of internal french doors were delivered, the external french doors were installed and the doorway from the hall to the dining room was opened up for the french doors.