Saturday 9 November 2019

New outdoor bench unit

 Designed for bbq prep but also a great place to wash paintbrushes.

Thursday 17 October 2019

The last roofing

Dean's back to do the last of the reroofing, including installing a skylight above the front door to let more light into the hallway.




And Matthew's started digging the holes for the new guest room deck that Dean will build next.



Thursday 28 March 2019

Friday 22 March 2019

Door handles installed

Dean installed the door handles and push panels and Matthew restained the doors.



 

Monday 18 March 2019

Guest room painting

Starting to paint the guest room so that we can put the curtains back up. The room has recently been replastered to fix faults and changes.

Ceiling gibseal done:


Friday 15 March 2019

French door architraves on

Dean put the remaining architraves around the dining room french doors and also added the skirting boards for that room.



Wednesday 6 March 2019

The last plastering

The dining room, hall and some bits of the guest room are being plastered this week.



Tuesday 8 January 2019

Water tank

Installation of a 30,000 litre water tank to collect rain water started today.