Wednesday, 14 March 2018
Tuesday, 13 March 2018
First skylights installed
There will be 7 skylights in all, all in the covered parts of the extension verandah. We night add one in the front verandah too.
Friday, 9 March 2018
It's all coming together
Dean, Ryan and Cody worked on a variety of inside and outside tasks today. Next week, while we are away in Northland, the last two windows and the bifold doors for the extension should be installed.
Thursday, 8 March 2018
Inside work
Poor weather over the last couple of days so lots done indoors: Pantry framework, ensuite and kitchen floor constructed in the old laundry area and the opening made for the first of the two internal french doors.
Tuesday, 6 March 2018
Window day!!
As well as the first four new windows being installed in the extension today, Peter Allum installed the round leadlight window in the front door.
And Ryan and Cody installed the first four new windows in the extension.
And Ryan and Cody installed the first four new windows in the extension.
Friday, 2 March 2018
Windows day?
Hoping the windows will arrive today. Yesterday I picked up another 300 lineal metres of matai flooring boards so this morning Cody and I stacked them, plus the ones I had put in the shed a month ago, inside the extension which is mainly watertight and will be even more so if the windows are put in today.
Dean is working on the roof over the steps up to the verandah from near where the garage will eventually be.
The first four windows have arrived.
Dean is working on the roof over the steps up to the verandah from near where the garage will eventually be.
The first four windows have arrived.
Thursday, 1 March 2018
East weatherboards
Ryan put weatherboards on the east wall in anticipation of the windows arriving soon.
And we went to see Peter Allum in Featherston and the stained glass window for the front door.
And we went to see Peter Allum in Featherston and the stained glass window for the front door.