Thursday, 7 June 2018

Old scotias reused in lounge and ensuite.

Ryan put back the scotias he'd taken down from the lounge ceiling a year ago and used others for the ensuite.

Thursday, 31 May 2018

Plastering started

After a couple of days when there was just Dean here, today we had 3 plasterers, 2 builders, 1 joinery delivery man, 1 glazier and a plumber!

The plasterers started, the last set of french doors and the two sets of internal french doors were delivered, the external french doors were installed and the doorway from the hall to the dining room was opened up for the french doors.


Tuesday, 29 May 2018

Some of the decking timber arrived

Dean started gibbing the ensuite today.

The  timber for the decking structure was delivered.

Friday, 25 May 2018

Room gibbing finished

Just the ensuite to go, then the dining room and the last part of the hall.

Thursday, 24 May 2018