Ryan continued laying floorboards
While Dean has built the woodburner surround.
Friday, 6 April 2018
Thursday, 5 April 2018
Wednesday, 4 April 2018
Thursday, 29 March 2018
Floor, roof and footpath
The first underfloor insulation was laid, the roof was nearly completed and even the footpath outside started to be replaced.
It was all just too much action for some.
It was all just too much action for some.
Wednesday, 28 March 2018
One wall down and one wall up
Malcolm Jenkins from Recycled Rimu Furniture in Carterton is taking down (and taking away) the old back wall while Ryan is erecting the wall between the ensuite and new kitchen area.